Development programme

Details of the committed development projects are set out in the table below:

Development Status Cost to
complete as at
31 December 2007
£m
Eldon Square, Newcastle (60% interest) 57
Eldon Square West – restaurants and 22,000 sq. ft. retail. Completed in October 2006.
Eldon Square North – bus station and 48,000 sq. ft. retail. Bus station completed February 2007.
Retail on site; expected opening February 2008.
 
Eldon Square South – 410,000 sq. ft. retail extension including 175,000 sq. ft. Debenhams department store. On site July 2007.
Expected opening Spring 2010.
St David’s, Cardiff (50% interest) 186
967,500 sq. ft. extension.
Joint venture with Land Securities Group PLC.
On site. Expected opening Autumn 2009.
Other developments – CSC 34
Other developments – Capital & Counties 40
Total committed developments 317